Resource Portfolio Problem under Relaxed Resource Dedication

Policy in Multi-mode Multi-project Scheduling

Umut Beşikçi

Triodor ArGe Yazılım ve Bilişim Tic. Ltd. Şti.,

Aydınevler, Durak Sokak 7/9, Maltepe, 34854 Istanbul, Turkey

Email: umut.besikci@triodor.eu

Ümit Bilge*

Department of Industrial Engineering, Boğaziçi University,

Bebek, 34342 Istanbul, Turkey

Email: bilge@boun.edu.tr

*Corresponding author

Gündüz Ulusoy

Faculty of Engineering and Natural Sciences,

Sabancı University, Orhanlı, Tuzla, 34956 Istanbul, Turkey

Email: gunduz@sabanciuniv.edu

Abstract: The most common approach in the multi-project scheduling literature considers resources as a common pool shared among all projects. However, different resource management strategies may be required for different problem environments. We present the Relaxed Resource Dedication (RRD) policy, which prevents the sharing of resources among projects but allows resource transfers when a project starts after the completion of another one. We treat the case where the available amounts of resources -namely, the capacities- are decision variables subject to a limited budget. This capacity planning problem, called the Resource Portfolio Problem, is investigated under the RRD policy employing both renewable and nonrenewable resources with multiple modes of usage. A mixed integer linear programming model to minimize total weighted tardiness is proposed. To obtain some benchmark solutions for this hard problem, the branch and cut procedure of ILOG CPLEX is modified by customized branching strategies, feasible solution generation schemes and valid inequalities.

Keywords: Multi-mode Resource Constrained Multi-project Scheduling;

Resource Dedication; Resource Portfolio Allocation; Branch and Cut.

Appeared in International Journal of Mathematics in Operational Research (IJMOR), 14(4), 541-567, 2019.

Referanslar

Benzer Belgeler

The RPP in a multi-project environment determinates the general re- source capacities for a given total resource budget and the dedication of a set of resources to a set of

The parameters of NSGA-II, which are population size, generation number, crossover rate and mutation rate are determined with a detailed fine-tuning experiment.. In

In the last decades an extensive amount of work has been accomplished in developing exact and heuristic algorithms for the solution of resource constrained project scheduling

• A unique data set is generated for investigating the effects of the total number of activities, the due date tightness, the due date range, the number of

RPP in a multi-project environment covers the determination of general resource capacities for a given total resource budget, dedication of these resources to a set of projects

RPP in a multi-project environment is the determination of general re- source capacities for a given total resource budget, dedication of a set of resources to a set of projects

The proposed feasible solution generation procedure basically determines general resource capacities, resource dedication values and resource transfers (according to values of y vv

Although the characteristics of the projects and/or resources in a given problem can require different ways of managing the resources, the general approach regarding resource